October 2019 Construction Update

new abbotsford condos for sale

This month at Ventura we are pleased to report that the site is now mobilized with a site trailer and construction team in place.

The shoring crew is making good progress with the site prep which includes soil anchoring with a shotcrete facing, that reinforces the vertical surface of the excavated site.  Once that process is completed, the large crane will be set up and forming of the concrete parkade will begin.   Every week, we are also signing new contracts for various trades and materials that will be needed on site in 2020, so things are moving forward with good momentum.

Check back here for more updates in the months to come!